S.# Purchase Order # Description
1 4540184239 KEMYA SITE SUPPORT
2 4540149319 FAT SUPPORT
3 4540210901 HAWAIYAH SITE SUPPORT
4 4540248301 DCS ESD  Upgrading for Saudi Aramco UWIP NO. 1&2
5 4540250444
6 4540231673
7 4540235164
8 4540250967 Supply , Integration , Installation testing & commissioning of Network Scope Construction work at LLDP Plant , Networking Equipment , Kemya Sabic Jubail
9 4540184239 Supply & Installation of Conduit with fittings and supports, laying& termination of control cables, installation of Junction boxes
10 4540223477 ESD Cabinets Integration
11 175525 Supply & Installation of Generator 15kva, 500Kva, 410 Kw
12 4540211244 ESD Cabinets Integration
13 4540242773 Supply installation of blank console plate and installation of new enunciators, Installation of Cat5 Cable
14 179037 Supply & Installation of 563 KVA Generator
15 4540250444 SAT & Commissioning Support
16 4540254924 ESD Cabinets Integration
17 4540264349 MATERIAL SUPPLY
18 4540281479 ESD Cabinets Integration
19 4540270308 ESD Cabinets Integration
20 4540270307 ESD Cabinets Integration
21 4540266668 ESD Cabinets Integration
22 4540254928 ESD Cabinets Integration
23 4540270307 ESD Cabinets Integration
24 4540289416 Construction scope for Transfer of the OTS from TTF to GSB @ SATROP
25 4540291060 ESD Cabinets Integration
26 4540281479 DCS ESD Upgrading for Saudi Aramco UWIP NO. 4,5
27 4540254926 ESD  Upgrading for SABIC Al Bayrouni
28 4540266672
29 4540266667
30 4540270305
31 4540339143 ESD Cabinets Integration
32 4540331292 Integration & FAT Support / SAT & Commissioning Support
33 4540320342 ESD Cabinets Integration
34 4540316442 Integration & FAT Support / SAT & Commissioning Support
35 4540314393 Integration & FAT Support / SAT & Commissioning Support
36 4540320342 ESD Cabinets Integration
37 4540304939 ESD Cabinets Integration
38 4540291060 ESD Cabinets Integration
39 4540350951 YANSAB PROJECT
40 4540331292 Integration & FAT Support / SAT & Commissioning Support
41 4540355653 ESD Cabinets Integration
42 4540365162 ESD Cabinets Integration
43 4540355112 Integration & FAT Support / SAT & Commissioning Support
44 4540380433 Integration & FAT Support / SAT & Commissioning Support
45 4540362600 Integration & FAT Support / SAT & Commissioning Support
46 4540378488 LCP PANEL integration
47 4540379781 Integration & FAT Support / SAT & Commissioning Support
48 4540350575 DCS UPGRADING WORK @ OF SHEDGUM GAS PLANT AND UTHMANIYAH GAS PLANT SAUDI ARAMCO
49 4700101004 Integration & FAT Support / SAT & Commissioning Support
50 4540350501 DCS UPGRADING FOR SULPHUR LOADING PLANT AT SAUDI ARAMCO HARAD GAS PLANT NGL
51 4540358838 Integration & FAT Support / SAT & Commissioning Support QA/QC
52 Construction Support @ EDC SADAF
53 4540340835 NGPD Control System Upgrade
54 4540339143 Integration & FAT Support / SAT & Commissioning Support
55 4540377784 PETRO-RABIGH Control System Upgrade
S.# Purchase Order # Description
1 4540374953 SADAF SEA WATER COOLING ESD Upgrade Project
2  4540387245 ESD & CCS UPGRADE INSTALLATION @ ABQAIQ GOSP-2 SAUDI ARAMCO
3 4540387914 Anti Surge CCS Upgrade Project @ SABIC SADAF
4  4540392661 UDD Gas Turbines TMC Upgrade Project
5  Letter of Intent Received 3EG DCS Upgrade Project, SABIC Sharq
6  Letter of Intent Received DCS Servers & Work Stations Upgrade @ Haradh Gas Plant
  • PSC has the Quality plan in Place
  • PSC has the Quality Control program in Place
  • PSC has the ability to consistently provide Product that meets customer and applicable statutory and regulatory requirements
  • PSC has the ability to enhance customer satisfaction through the effective application of the system, including processes for continual improvement of the system and the assurance of conformity to customer and applicable statutory and regulatory requirements
  • Clients has conducted a quality audit of our work on the projects executed
  • PSC has the routine schedule to conduct internal quality audits.
  • PSC has a written safety plan and is provided to all employees
  • PSC Safety policy statement is provided to all employees and posted in prominent locations at all offices
  • PSC new employee orientation includes a safety component
  • PSC develops a site specific safety plan for each project site
  • As a routine PSC Field supervisors attend site safety meetings weekly & conducts daily Site toolbox safety meetings